ACCA LW · Chapter 4 · Question 4 of 10
A contract states that if the builder finishes late it will pay 2,000 per week of delay. The amount was set after considering the client's likely losses. What is the clause most likely to be?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: A) An enforceable liquidated damages clause
Explanation
Under Cavendish Square Holding v Makdessi (with ParkingEye v Beavis), a clause requiring payment on breach is a penalty only if it imposes a detriment on the party in breach out of all proportion to any legitimate interest of the innocent party in performance of the primary obligation. A sum fixed by a genuine attempt to estimate the client's likely loss, the approach associated with Dunlop Pneumatic Tyre v New Garage, protects a legitimate interest and is clearly not out of all proportion, so it is enforceable as liquidated damages. The agreed sum is then recoverable whether actual loss turns out greater or smaller. The clause does not exclude liability and is not a condition precedent.
More Breach of contract and remedies MCQs
- Q6In which situation is a court most likely to order specific performance?
- Q7An actress contracted exclusively with a film company and agreed not to act for any other company during the contract. She left to work…
- Q8An author was engaged to write a book for a series, and after he had done part of the work the publisher abandoned the series. What remedy…
- Q9Under the Limitation Act 1980, what is the normal limitation period for an action for breach of a simple contract?
- Q10Which of the following statements about damages for breach of contract is correct?
