Under the Limitation Act 1980, what is the normal limitation period for an action for breach of a simple contract?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: D) Six years from the date on which the cause of action accrued
Explanation
An action for breach of a simple contract must normally be brought within six years of the date on which the breach occurred. For a contract made by deed (a speciality), the period is twelve years. Three years applies to personal injury claims, which are a separate category.
More Breach of contract and remedies MCQs
- Q1Before the date for performance, one party clearly states that it will not perform its obligations. What is this called and what may the…
- Q2Under the first limb of the rule in Hadley v Baxendale, which losses are recoverable for breach of contract?
- Q3A laundry company bought a boiler that was delivered five months late. The seller knew the laundry needed it urgently but did not know of…
- Q4A contract states that if the builder finishes late it will pay 2,000 per week of delay. The amount was set after considering the client's…
- Q5Which of the following best describes the innocent party's duty to mitigate loss after a breach of contract?