ACCA PM · Chapter 12 · Question 10 of 12
Which of the following is a recognised problem with separating variances into planning and operational elements?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: A) Managers may try to claim that adverse variances are due to planning errors outside their control
Explanation
Revised standards are set with hindsight and involve judgement, so managers have an incentive to argue that poor results are planning (uncontrollable) issues. Establishing a realistic revised standard can also be time-consuming. Planning and operational analysis can be applied to sales, material, labour and overhead variances.
More Standard costing and variance analysis MCQs
- Q12A company's standard selling price for product T is $50 per unit. During the period it sold 1,900 units at an average price of $48 per…
- Q1Which type of standard assumes perfect operating conditions, with no allowance for wastage, idle time or machine breakdowns?
- Q2A company bought and used 4,200 kg of material at a total cost of $23,100. The standard price is $5.20 per kg and the standard usage is 4…
- Q3Product W is made by mixing two materials. The standard input to produce 9 kg of W is 6 kg of D at $4 per kg and 4 kg of E at $7 per kg…
- Q4Product W is made by mixing two materials. The standard input to produce 9 kg of W is 6 kg of D at $4 per kg and 4 kg of E at $7 per kg…
