The CA Hub

ACCA PM · Chapter 12 · Question 10 of 12

Which of the following is a recognised problem with separating variances into planning and operational elements?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: A) Managers may try to claim that adverse variances are due to planning errors outside their control

Explanation

Revised standards are set with hindsight and involve judgement, so managers have an incentive to argue that poor results are planning (uncontrollable) issues. Establishing a realistic revised standard can also be time-consuming. Planning and operational analysis can be applied to sales, material, labour and overhead variances.

All 12 questions in Chapter 12Standard costing and variance analysis MCQs with answers

More Standard costing and variance analysis MCQs

Sponsored slot availableRun a CA academy or hiring firm? Put your name in front of students preparing for this exam.Advertise →