ACCA PM · Chapter 12 · Question 9 of 12
The standard labour time is 2 hours per unit at $12 per hour. Following new safety regulations that were not foreseen when the standard was set, a realistic standard would have been 2.5 hours per unit. Output was 1,800 units and 4,300 hours were worked. What is the labour efficiency operational variance?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: A) $2,400 favourable
Explanation
Revised standard hours for actual output = 1,800 x 2.5 = 4,500 hours. Operational efficiency variance = (4,500 - 4,300) x $12 = $2,400 favourable. The planning variance is (3,600 - 4,500) x $12 = $10,800 adverse, giving a total efficiency variance of $8,400 adverse.
More Standard costing and variance analysis MCQs
- Q11A purchasing manager buys a cheaper, lower-quality grade of material than standard. Which combination of variances is most likely to arise?
- Q12A company's standard selling price for product T is $50 per unit. During the period it sold 1,900 units at an average price of $48 per…
- Q1Which type of standard assumes perfect operating conditions, with no allowance for wastage, idle time or machine breakdowns?
- Q2A company bought and used 4,200 kg of material at a total cost of $23,100. The standard price is $5.20 per kg and the standard usage is 4…
- Q3Product W is made by mixing two materials. The standard input to produce 9 kg of W is 6 kg of D at $4 per kg and 4 kg of E at $7 per kg…
