Which of the following costs is most likely to be driven by the number of production batches rather than the number of units produced?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: C) Machine set-up costs

Explanation

Set-up costs are incurred each time a new batch is started, regardless of how many units the batch contains, so they are batch-level costs. Direct materials, machine running power and per-unit royalties all vary with the number of units.