ACCA PM · Chapter 2 · Question 2 of 9
Delta Co makes two products, X and Y. Budgeted overheads are: machine set-ups $120,000; materials handling $80,000; machining $200,000. Product X: 4,000 units, 2 machine hours per unit, 30 set-ups, 50 material movements. Product Y: 1,000 units, 4 machine hours per unit, 50 set-ups, 110 material movements. Using activity-based costing, what is the overhead cost per unit of product Y (to the nearest cent)?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: A) $196.67
Explanation
Set-up rate = $120,000 / 80 = $1,500; handling rate = $80,000 / 160 = $500; machining rate = $200,000 / 12,000 hours = $16.6667 per hour. Y overheads = (50 x $1,500) + (110 x $500) + (4,000 hours x $16.6667) = $75,000 + $55,000 + $66,667 = $196,667. Per unit = $196,667 / 1,000 = $196.67.
More Activity-based costing MCQs
- Q4Delta Co makes two products, X and Y. Budgeted overheads are: machine set-ups $120,000; materials handling $80,000; machining $200,000…
- Q5In activity-based costing, what is a cost driver?
- Q6In which of the following situations is activity-based costing most likely to give significantly different product costs from traditional…
- Q7Which of the following costs is most likely to be driven by the number of production batches rather than the number of units produced?
- Q8Quality inspection costs are budgeted at $90,000 for the year, with 600 inspections expected. Product Z will be produced in a run of 2,500…
