A cost gap has been identified for a new kitchen appliance. Which of the following actions is most consistent with closing the gap through value engineering?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: A) Removing design features that customers do not value and using standardised components
Explanation
Value engineering redesigns the product to reduce cost without reducing the value perceived by customers, for example by removing unvalued features or using common components. Raising price above the market level or abandoning the profit target defeats the purpose of target costing, and cutting valued features reduces customer value.
More Target costing and life-cycle costing MCQs
- Q6A product has a three-year life. Design costs of $300,000 are incurred before launch. Expected sales and variable costs are: Year 1…
- Q7At which stage of a product's life are the majority of its life-cycle costs committed (locked in)?
- Q8Which of the following is a benefit of life-cycle costing compared with traditional period-based cost reporting?
- Q9During which stage of the product life cycle is a product likely to face slowing sales growth, intense price competition and a focus on…
- Q1A company plans to launch a product at a market price of $80. It requires a profit margin of 25% of the selling price. The current…