ACCA PM · Chapter 4 · Question 5 of 10

Sigma Co has a bottleneck in its painting process. Details of three products are: Product A: price $40, direct materials $16, painting time 12 minutes Product B: price $55, direct materials $25, painting time 20 minutes Product C: price $30, direct materials $6, painting time 15 minutes Using throughput accounting, in what order should the products be ranked for production?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: D) A, C, B

Explanation

Throughput per bottleneck hour: A = ($40 - $16) / (12/60) = $120; B = ($55 - $25) / (20/60) = $90; C = ($30 - $6) / (15/60) = $96. Ranking by return per bottleneck hour gives A ($120), C ($96), then B ($90). Ranking by throughput per unit would wrongly put B first.

All 10 questions in Chapter 4Throughput accounting and environmental management accounting MCQs with answers

More Throughput accounting and environmental management accounting MCQs

Sponsored slot availableRun a CA academy or hiring firm? Put your name in front of students preparing for this exam.Advertise →