CA Inter P4 · Chapter 12 · Question 7 of 10
Budgeted fixed overheads are ₹4,80,000 for a budgeted output of 24,000 units. Actual output was 22,500 units. The fixed overhead volume variance is:
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: C) ₹30,000 (Adverse)
Explanation
Standard fixed overhead rate = ₹4,80,000 / 24,000 = ₹20 per unit. Volume variance = (actual output - budgeted output) x standard rate = (22,500 - 24,000) x ₹20 = -₹30,000, i.e. ₹30,000 Adverse, because output fell short of budget and fixed overheads were under-absorbed.
More Standard Costing MCQs
- Q9A standard that assumes perfect operating conditions, with no allowance for wastage, machine breakdowns or idle time, is called a(n):
- Q10An adverse material price variance is normally the responsibility of the:
- Q1Standard material for one unit of product is 4 kg at ₹25 per kg. Actual output was 2,000 units, using 8,300 kg purchased and consumed at…
- Q2Using the same data (standard 4 kg at ₹25 per unit; actual output 2,000 units; actual usage 8,300 kg at ₹24), the material usage variance…
- Q3With the same data, the material cost variance is:
