CA Inter P4 · Chapter 12 · Question 8 of 10
Budgeted fixed overheads are ₹4,80,000 for a budgeted output of 24,000 units. Actual fixed overheads incurred were ₹4,95,000 and actual output was 22,500 units. The fixed overhead cost variance, and its split into expenditure and volume variances, is:
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: D) ₹45,000 (A), being expenditure ₹15,000 (A) and volume ₹30,000 (A)
Explanation
Standard rate = ₹4,80,000 / 24,000 = ₹20 per unit. Overheads absorbed = 22,500 x ₹20 = ₹4,50,000. Cost variance = absorbed - actual = ₹4,50,000 - ₹4,95,000 = -₹45,000, i.e. ₹45,000 Adverse. Expenditure variance = budgeted - actual = ₹4,80,000 - ₹4,95,000 = ₹15,000 Adverse. Volume variance = absorbed - budgeted = ₹4,50,000 - ₹4,80,000 = ₹30,000 Adverse. Check: 15,000 + 30,000 = 45,000.
More Standard Costing MCQs
- Q10An adverse material price variance is normally the responsibility of the:
- Q1Standard material for one unit of product is 4 kg at ₹25 per kg. Actual output was 2,000 units, using 8,300 kg purchased and consumed at…
- Q2Using the same data (standard 4 kg at ₹25 per unit; actual output 2,000 units; actual usage 8,300 kg at ₹24), the material usage variance…
- Q3With the same data, the material cost variance is:
- Q4Standard labour per unit is 3 hours at ₹60 per hour. Actual output was 1,800 units. Workers were paid for 5,700 hours at ₹62 per hour…
