Unit (single or output) costing is most suitable for:

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: A) A cement factory producing a single homogeneous product

Explanation

Unit costing is used where production is continuous and units are identical, such as cement, bricks, mining or a brewery, so cost per unit = total cost / units produced. Ship-building and printing orders use job or contract-type costing, and a bus service uses service (operating) costing.