CAF-5 · Chapter 18 · Question 2 of 20
(CVP Analysis & Multi-Product Limiting Factor) Gamma Ltd produces two products, G1 and G2. G1 has a selling price of Rs. 150, variable cost of Rs. 90, and requires 3 machine hours. G2 has a selling price of Rs. 200, variable cost of Rs. 120, and requires 5 machine hours. Total fixed costs are Rs. 300,000. The maximum market demand is 8,000 units for G1 and 6,000 units for G2. If maximum machine hours available are 39,000, what is the maximum net profit Gamma Ltd can achieve?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: B) Rs. 420,000
Explanation
Rank products by CM per limiting factor. G1 CM = 60; CM/hr = 60/3 = Rs. 20/hr. G2 CM = 80; CM/hr = 80/5 = Rs. 16/hr. Priority: G1 first. G1 demand = 8,000 units * 3 hrs = 24,000 hrs. Remaining hours = 39,000 - 24,000 = 15,000 hrs. G2 production = 15,000 / 5 = 3,000 units. Total CM = (8,000 * 60) + (3,000 * 80) = 480k + 240k = Rs. 720,000. Net Profit = 720k - Fixed Costs (300k) = Rs. 420,000.
More Mixed Practice Challenge II MCQs
- Q4(Relevant Costing & Inventory Valuation) A special contract requires 800 kg of Material Alpha. The company has 500 kg of Alpha in…
- Q5(Relevant Costing & Labour Shortage) A special order requires 500 hours of skilled labour. The workforce is currently operating at full…
- Q6(Inventory Management & Quantity Discounts) The annual demand for a raw material is 30,000 units. The ordering cost is Rs. 800 per order…
- Q7(Process Costing: Weighted Average & Variances) Opening WIP is 2,000 units (40% complete for conversion) valued at Rs. 12,000 for…
- Q8(Joint Products & By-Products with NRV) A joint process incurs Rs. 400,000 and yields 10,000 kg of M, 5,000 kg of N, and 2,000 kg of…
