CAF-5 · Chapter 18 · Question 1 of 20
(Target Costing & Learning Curve) A company is developing a new specialized product with a target selling price of Rs. 2,000 per unit. The company requires a profit margin of 25% on sales. The first batch of 50 units will take 200 labour hours in total. The workforce is expected to follow a 90% learning curve (index = -0.152) until the 4th batch is completed. If the standard labour rate is Rs. 150 per hour and other variable costs total Rs. 800 per unit, what is the expected target cost gap for the first 4 batches (200 units)?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: D) Rs. 0 (Expected cost is below target cost)
Explanation
Target Revenue for 200 units = 200 * Rs. 2,000 = Rs. 400,000. Target Profit (25% on sales) = Rs. 100,000. Total Target Cost = Rs. 300,000. Expected Cost Calculation: Learning curve for 4 batches (200 units): Y=ax^b. Y=200 hours*4^-0.152 = 200*0.81 = 162 hours per batch. Total expected hours for 4 batches = 162*4 = 648 hours. Labour cost = 648 hours*Rs. 150 = Rs. 97,200. Variable costs = 200 units*Rs. 800 = Rs. 160,000. Total Expected Cost = 97,200 + 160,000 = Rs. 257,200. Since expected cost (257,200) is lower than Target Cost (300,000), there is NO gap.
More Mixed Practice Challenge II MCQs
- Q3(Marginal/Absorption Costing & Variance Analysis) Budgeted fixed overheads for the year were Rs. 500,000 based on a budgeted capacity of…
- Q4(Relevant Costing & Inventory Valuation) A special contract requires 800 kg of Material Alpha. The company has 500 kg of Alpha in…
- Q5(Relevant Costing & Labour Shortage) A special order requires 500 hours of skilled labour. The workforce is currently operating at full…
- Q6(Inventory Management & Quantity Discounts) The annual demand for a raw material is 30,000 units. The ordering cost is Rs. 800 per order…
- Q7(Process Costing: Weighted Average & Variances) Opening WIP is 2,000 units (40% complete for conversion) valued at Rs. 12,000 for…
