CIMA BA2 · Chapter 7 · Question 4 of 14
A team was paid $63,900 for 3,600 hours worked. The standard rate is $17.50 per hour and each unit should take 3 standard hours. Output was 1,150 units. What is the labour efficiency variance?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: B) $2,625 adverse
Explanation
Standard hours for actual output = 1,150 x 3 = 3,450 hours. Actual hours = 3,600. Excess hours = 150 x $17.50 = $2,625 adverse. (Separately, the rate variance is $63,000 - $63,900 = $900 adverse.)
More Standard costing and variance analysis MCQs
- Q6Variable production overheads are absorbed at $6 per labour hour worked. In a period, 4,700 labour hours were worked and actual variable…
- Q7Budgeted fixed production overheads for a period were $120,000. Actual fixed production overheads were $126,500. What is the fixed…
- Q8A company uses standard MARGINAL costing. Budgeted fixed production overheads were $120,000, based on budgeted production of 10,000 units…
- Q9A company sold 5,200 units for total revenue of $247,000. The standard selling price is $50 per unit. What is the sales price variance?
- Q10Budgeted sales were 6,000 units but actual sales were 5,200 units. The standard selling price is $50, the standard variable cost is $28…
