The CA Hub

CIMA BA2 · Chapter 9 · Question 2 of 11

A project could produce a profit of $40,000 (probability 0.3), a profit of $25,000 (probability 0.5) or a loss of $10,000 (probability 0.2). What is the expected value of the project's profit?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: D) $22,500

Explanation

Expected value = sum of (outcome x probability) = ($40,000 x 0.3) + ($25,000 x 0.5) + (-$10,000 x 0.2) = $12,000 + $12,500 - $2,000 = $22,500.

All 11 questions in Chapter 9Risk and uncertainty in decision making MCQs with answers

More Risk and uncertainty in decision making MCQs

Sponsored slot availableRun a CA academy or hiring firm? Put your name in front of students preparing for this exam.Advertise →