CIMA BA2 · Chapter 9 · Question 3 of 11
A risk-neutral manager must choose between two mutually exclusive projects: Project X: profit $60,000 (probability 0.4) or $20,000 (probability 0.6) Project Y: profit $90,000 (probability 0.3), $10,000 (probability 0.5) or a loss of $5,000 (probability 0.2) Which project should be chosen and what is its expected profit?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: C) Project X, with an expected profit of $36,000
Explanation
EV of X = ($60,000 x 0.4) + ($20,000 x 0.6) = $24,000 + $12,000 = $36,000. EV of Y = ($90,000 x 0.3) + ($10,000 x 0.5) - ($5,000 x 0.2) = $27,000 + $5,000 - $1,000 = $31,000. A risk-neutral manager chooses the higher expected value, so Project X.
More Risk and uncertainty in decision making MCQs
- Q5A manager prefers an investment with a certain return of $50,000 to an alternative offering an equal chance of $0 or $110,000. What is the…
- Q6The weekly demand for a product is normally distributed with a mean of 500 units and a standard deviation of 40 units. What is the…
- Q7The weekly demand for a product is normally distributed with a mean of 500 units and a standard deviation of 40 units. What is the…
- Q8Two machines operate independently. The probability that machine 1 breaks down in a week is 0.10 and the probability that machine 2 breaks…
- Q9A company budgets to sell 20,000 units at $15 each. Variable cost is $9 per unit and fixed costs are $84,000. By what percentage could the…
