Using activity-based budgeting, a plant plans to run 120 production batches next year. Each batch requires 2 machine setups, and each setup consumes resources costing $425. What is the budgeted cost of the setup activity?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: B) $102,000

Explanation

Activity-based budgeting starts from the planned volume of the activity driver. Setups = 120 batches x 2 = 240 setups. Budgeted cost = 240 x $425 = $102,000.