ICAEW BL · Chapter 4 · Question 5 of 10
On 1 March, Danby Ltd tells Ellery Ltd that it will not deliver goods due on 1 September. Ellery Ltd chooses to affirm the contract and wait. In June, before the delivery date and through no fault of either party, a new law makes it illegal to export the goods to Ellery's country. Can Ellery Ltd recover damages from Danby Ltd for non-delivery?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: A) No, because by affirming, Ellery kept the contract alive for both parties, and the later frustrating event discharged Danby as well
Explanation
Danby's statement was an anticipatory breach. Ellery could have accepted the repudiation and sued at once (Hochster v De La Tour). Instead it affirmed, so the contract remained in force for both parties, with the risks that brings. In Avery v Bowden the innocent party affirmed and the contract was then frustrated by the outbreak of war, which discharged both parties, so no damages were recoverable. Here the supervening illegality frustrates the contract in the same way, and Ellery has lost its claim for the earlier repudiation.
More Breach of contract and remedies MCQs
- Q7Corvan Ltd hires Isla to redesign its website for a fixed fee payable on completion. Halfway through, Corvan wrongfully tells Isla to stop…
- Q8A contract made by deed required Norland Ltd to carry out works for Pike Ltd. Norland breached the contract eight years ago and Pike Ltd…
- Q9Lowther Ltd hires a conference centre for a three-day trade fair. A week before the event, through no fault of either party, the centre is…
- Q10Harrow Ltd contracts to buy 500 units from a supplier at £40 each. The supplier fails to deliver. On the delivery date the same units are…
- Q1What is the general aim of an award of damages for breach of contract?
