ICAEW BL · Chapter 4 · Question 10 of 10
Harrow Ltd contracts to buy 500 units from a supplier at £40 each. The supplier fails to deliver. On the delivery date the same units are freely available in the market at £46 each. Harrow waits a week and then buys replacements at £49 each, although nothing stopped it buying earlier. Applying the market price rule, how much can Harrow recover as damages for non-delivery?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: C) £3,000
Explanation
Where there is an available market, damages for non-delivery are normally the difference between the contract price and the market price at the date when delivery should have been made. Here that is (£46 − £40) × 500 = £6 × 500 = £3,000. The extra £3 per unit from waiting a week was avoidable and is not recoverable. £4,500 uses the later £49 price, and £20,000 and £23,000 wrongly use the whole contract price or the whole market price.
More Breach of contract and remedies MCQs
- Q2Tallis Bakery Ltd orders a new industrial oven from Vane Engineering, which delivers it six weeks late. As a result Tallis loses (1) its…
- Q3Fenwick Events cancels a block booking of 40 hotel rooms in breach of contract, three months before the event date. The hotel accepts the…
- Q4A software licence obliges the licensee to pay £50,000 if it breaches a non-disclosure clause. The licensor's business depends on the…
- Q5On 1 March, Danby Ltd tells Ellery Ltd that it will not deliver goods due on 1 September. Ellery Ltd chooses to affirm the contract and…
- Q6In which of the following situations is a court most likely to order specific performance?
