PRC-3 · Chapter 1 · Question 10 of 61
A local community group is highly concerned about the noise from a new construction project but has little legal power to stop it. Under Mendelow's Matrix, how should the construction firm manage this group?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: A) Keep informed
Explanation
Groups with high interest but low power should be kept informed to maintain good relations and prevent them from gaining power to disrupt the business.
More Nature of Business MCQs
- Q12The board of directors at Horizon Pharmaceuticals states their core purpose is 'To improve global health by creating accessible…
- Q13A regional manager at a retail chain aims to 'reduce customer wait times by 15% before the end of the third quarter.' What is this an…
- Q14A commercial agricultural business utilizes vast tracts of soil, tractors, hired workers, and the owner's risk-taking ability. Which…
- Q15Which of the following best describes the fundamental role of 'entrepreneurship' as a factor of production?
- Q16A local charity is formed to provide clean drinking water to remote villages. Since it does not distribute profits to owners, how should…