A government environmental regulator has significant power over a proposed new chemical plant and has publicly stated it will scrutinise the plans closely. Under Mendelow's matrix, how should the company treat the regulator?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: B) As a key player whose views must be considered and managed closely

Explanation

The regulator has high power (it can block or condition the project) and has shown high interest by announcing close scrutiny. High power and high interest place it in the key player quadrant, so its views should be actively considered and managed. Keeping it merely satisfied would underestimate its expressed interest.