The CA Hub

CA Inter P4 · Chapter 12 · Question 4 of 10

Standard labour per unit is 3 hours at ₹60 per hour. Actual output was 1,800 units. Workers were paid for 5,700 hours at ₹62 per hour, including 120 hours of abnormal idle time. The labour rate variance is:

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: B) ₹11,400 (Adverse)

Explanation

Labour rate variance = (standard rate - actual rate) x actual hours paid = (₹60 - ₹62) x 5,700 = -₹11,400, i.e. ₹11,400 Adverse. The rate variance is computed on all hours paid, including idle hours.

All 10 questions in Chapter 12Standard Costing MCQs with answers

More Standard Costing MCQs

Sponsored slot availableRun a CA academy or hiring firm? Put your name in front of students preparing for this exam.Advertise →