Standard labour per unit is 3 hours at ₹60 per hour. Actual output was 1,800 units. Workers were paid for 5,700 hours at ₹62 per hour, including 120 hours of abnormal idle time. The labour rate variance is:
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: B) ₹11,400 (Adverse)
Explanation
Labour rate variance = (standard rate - actual rate) x actual hours paid = (₹60 - ₹62) x 5,700 = -₹11,400, i.e. ₹11,400 Adverse. The rate variance is computed on all hours paid, including idle hours.
More Standard Costing MCQs
- Q6The standard mix for a product is material X 60% at ₹20 per kg and material Y 40% at ₹35 per kg. In a period, actual input was 5,000 kg…
- Q7Budgeted fixed overheads are ₹4,80,000 for a budgeted output of 24,000 units. Actual output was 22,500 units. The fixed overhead volume…
- Q8Budgeted fixed overheads are ₹4,80,000 for a budgeted output of 24,000 units. Actual fixed overheads incurred were ₹4,95,000 and actual…
- Q9A standard that assumes perfect operating conditions, with no allowance for wastage, machine breakdowns or idle time, is called a(n):
- Q10An adverse material price variance is normally the responsibility of the: