ACCA FM · Chapter 9 · Question 6 of 8
A project costs $70,000 now. The year 1 cash inflow will be $50,000 (probability 0.6) or $30,000 (probability 0.4). Independently, the year 2 cash inflow will be $60,000 (probability 0.7) or $40,000 (probability 0.3). The discount rate is 10% (DFs 0.909 and 0.826). What is the probability that the project will have a negative NPV?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: A) 12%
Explanation
NPVs of the four combinations: (50,000; 60,000) +25,010; (50,000; 40,000) +8,490; (30,000; 60,000) +6,830; (30,000; 40,000) -9,690. Only the last combination is negative, with joint probability 0.4 x 0.3 = 0.12, i.e. 12%. The other options use single-period probabilities or the wrong combination.
More Risk and uncertainty in investment appraisal MCQs
- Q8Which of the following is a limitation of using expected NPV to decide whether to accept a one-off project?
- Q1A project has an NPV of $42,000. The present value of sales revenue is $600,000, the present value of contribution is $280,000 and the…
- Q2In sensitivity analysis, what does the maximum cost of capital at which a project remains acceptable equal?
- Q3A project has the following possible NPVs: -$20,000 with probability 0.3, $40,000 with probability 0.5 and $90,000 with probability 0.2…
- Q4Which of the following correctly distinguishes risk from uncertainty in investment appraisal?
