ACCA FM · Chapter 9 · Question 7 of 8
A project has an initial investment of $250,000 and an NPV of $30,000. By what percentage could the initial investment increase before the project ceased to be worthwhile?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: D) 12.0%
Explanation
The initial investment occurs at time 0, so its present value equals its cost. Sensitivity = NPV / PV of investment = 30,000 / 250,000 = 12.0%. Dividing by the PV of inflows (280,000) gives 10.7%, which is the sensitivity of the inflows, not the investment.
More Risk and uncertainty in investment appraisal MCQs
- Q1A project has an NPV of $42,000. The present value of sales revenue is $600,000, the present value of contribution is $280,000 and the…
- Q2In sensitivity analysis, what does the maximum cost of capital at which a project remains acceptable equal?
- Q3A project has the following possible NPVs: -$20,000 with probability 0.3, $40,000 with probability 0.5 and $90,000 with probability 0.2…
- Q4Which of the following correctly distinguishes risk from uncertainty in investment appraisal?
- Q5Which of the following is a limitation of sensitivity analysis?
