The CA Hub

ACCA FM · Chapter 9 · Question 7 of 8

A project has an initial investment of $250,000 and an NPV of $30,000. By what percentage could the initial investment increase before the project ceased to be worthwhile?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: D) 12.0%

Explanation

The initial investment occurs at time 0, so its present value equals its cost. Sensitivity = NPV / PV of investment = 30,000 / 250,000 = 12.0%. Dividing by the PV of inflows (280,000) gives 10.7%, which is the sensitivity of the inflows, not the investment.

All 8 questions in Chapter 9Risk and uncertainty in investment appraisal MCQs with answers

More Risk and uncertainty in investment appraisal MCQs

Sponsored slot availableRun a CA academy or hiring firm? Put your name in front of students preparing for this exam.Advertise →