The CA Hub

ACCA FM · Chapter 9 · Question 2 of 8

In sensitivity analysis, what does the maximum cost of capital at which a project remains acceptable equal?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: B) The project's internal rate of return

Explanation

The NPV of a conventional project falls as the discount rate rises and becomes zero at the IRR. The sensitivity of the project to the cost of capital is therefore measured by comparing the IRR with the current cost of capital: the difference is the margin of safety.

All 8 questions in Chapter 9Risk and uncertainty in investment appraisal MCQs with answers

More Risk and uncertainty in investment appraisal MCQs

Sponsored slot availableRun a CA academy or hiring firm? Put your name in front of students preparing for this exam.Advertise →