ACCA FM · Chapter 9 · Question 3 of 8
A project has the following possible NPVs: -$20,000 with probability 0.3, $40,000 with probability 0.5 and $90,000 with probability 0.2. What is the expected NPV?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: A) $32,000
Explanation
Expected NPV = (-20,000 x 0.3) + (40,000 x 0.5) + (90,000 x 0.2) = -6,000 + 20,000 + 18,000 = $32,000. The simple average of the three outcomes ($36,667) ignores the probabilities, and treating the loss as positive gives $44,000.
More Risk and uncertainty in investment appraisal MCQs
- Q5Which of the following is a limitation of sensitivity analysis?
- Q6A project costs $70,000 now. The year 1 cash inflow will be $50,000 (probability 0.6) or $30,000 (probability 0.4). Independently, the…
- Q7A project has an initial investment of $250,000 and an NPV of $30,000. By what percentage could the initial investment increase before the…
- Q8Which of the following is a limitation of using expected NPV to decide whether to accept a one-off project?
- Q1A project has an NPV of $42,000. The present value of sales revenue is $600,000, the present value of contribution is $280,000 and the…
