CA Inter P4 · Chapter 12 · Question 5 of 10
Using the same data (standard 3 hours at ₹60 per unit; output 1,800 units; 5,700 hours paid of which 120 hours were abnormal idle time), the labour efficiency variance is:
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: A) ₹10,800 (Adverse)
Explanation
Standard hours for actual output = 1,800 x 3 = 5,400. Hours actually worked = 5,700 - 120 = 5,580. Efficiency variance = (standard hours - actual hours worked) x standard rate = (5,400 - 5,580) x ₹60 = ₹10,800 Adverse. Idle time of 120 hours x ₹60 = ₹7,200 Adverse is shown separately as the idle time variance.
More Standard Costing MCQs
- Q7Budgeted fixed overheads are ₹4,80,000 for a budgeted output of 24,000 units. Actual output was 22,500 units. The fixed overhead volume…
- Q8Budgeted fixed overheads are ₹4,80,000 for a budgeted output of 24,000 units. Actual fixed overheads incurred were ₹4,95,000 and actual…
- Q9A standard that assumes perfect operating conditions, with no allowance for wastage, machine breakdowns or idle time, is called a(n):
- Q10An adverse material price variance is normally the responsibility of the:
- Q1Standard material for one unit of product is 4 kg at ₹25 per kg. Actual output was 2,000 units, using 8,300 kg purchased and consumed at…