A company purchased 8,400 kg of material for $39,480. The standard price is $4.80 per kg. What is the material price variance?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: C) $840 favourable
Explanation
Standard cost of actual purchases = 8,400 x $4.80 = $40,320. Actual cost = $39,480. Material price variance = $40,320 - $39,480 = $840 favourable, because less was paid than the standard allows (actual price $4.70 per kg).
More Standard costing and variance analysis MCQs
- Q4A team was paid $63,900 for 3,600 hours worked. The standard rate is $17.50 per hour and each unit should take 3 standard hours. Output…
- Q5Employees were paid for 5,000 hours, but because of a machine breakdown only 4,700 hours were worked. The standard rate is $15 per hour…
- Q6Variable production overheads are absorbed at $6 per labour hour worked. In a period, 4,700 labour hours were worked and actual variable…
- Q7Budgeted fixed production overheads for a period were $120,000. Actual fixed production overheads were $126,500. What is the fixed…
- Q8A company uses standard MARGINAL costing. Budgeted fixed production overheads were $120,000, based on budgeted production of 10,000 units…