CIMA BA2 · Chapter 7 · Question 1 of 14
What is meant by an ATTAINABLE standard?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: C) A standard that can be achieved under efficient operating conditions, with allowances for normal losses, waste and idle time
Explanation
An attainable standard is challenging but achievable, including allowances for normal inefficiencies. An ideal standard assumes perfect conditions and may demotivate staff. A basic standard is left unchanged over long periods, and a current standard reflects present conditions.
More Standard costing and variance analysis MCQs
- Q3A company produced 2,000 units in a period. The standard usage is 4 kg of material per unit at a standard price of $4.80 per kg, and 8,300…
- Q4A team was paid $63,900 for 3,600 hours worked. The standard rate is $17.50 per hour and each unit should take 3 standard hours. Output…
- Q5Employees were paid for 5,000 hours, but because of a machine breakdown only 4,700 hours were worked. The standard rate is $15 per hour…
- Q6Variable production overheads are absorbed at $6 per labour hour worked. In a period, 4,700 labour hours were worked and actual variable…
- Q7Budgeted fixed production overheads for a period were $120,000. Actual fixed production overheads were $126,500. What is the fixed…