CIMA BA2 · Chapter 7 · Question 13 of 14
A standard costing operating statement starts with budgeted profit of $84,000. The variances for the period are: sales volume $6,000 adverse, sales price $4,500 favourable, total materials $3,200 adverse, total labour $1,800 favourable, fixed overhead expenditure $2,500 adverse. What is the actual profit?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: D) $78,600
Explanation
Actual profit = budgeted profit - adverse variances + favourable variances = $84,000 - $6,000 + $4,500 - $3,200 + $1,800 - $2,500 = $78,600.
More Standard costing and variance analysis MCQs
- Q1What is meant by an ATTAINABLE standard?
- Q2A company purchased 8,400 kg of material for $39,480. The standard price is $4.80 per kg. What is the material price variance?
- Q3A company produced 2,000 units in a period. The standard usage is 4 kg of material per unit at a standard price of $4.80 per kg, and 8,300…
- Q4A team was paid $63,900 for 3,600 hours worked. The standard rate is $17.50 per hour and each unit should take 3 standard hours. Output…
- Q5Employees were paid for 5,000 hours, but because of a machine breakdown only 4,700 hours were worked. The standard rate is $15 per hour…
