CIMA BA2 · Chapter 7 · Question 14 of 14

Variable production overheads are absorbed at $4 per labour hour worked, and the standard time is 2 labour hours per unit. In a period, employees were paid for 19,800 hours, but 600 of these hours were idle time because of a machine breakdown. Variable overheads are incurred only when labour is working. Actual output was 9,800 units. What is the variable overhead EFFICIENCY variance?

Test yourself: pick an answer

Reveal answer & explanation

Correct answer: C) $1,600 favourable

Explanation

Hours actually worked = 19,800 - 600 = 19,200. Standard hours for actual output = 9,800 x 2 = 19,600. Variable overhead efficiency variance = (19,600 - 19,200) x $4 = $1,600 favourable, because the output took fewer hours than standard. Using hours paid (19,800) would wrongly give $800 adverse; idle hours carry no variable overhead, so they are excluded.

All 14 questions in Chapter 7Standard costing and variance analysis MCQs with answers

More Standard costing and variance analysis MCQs

Sponsored slot availableRun a CA academy or hiring firm? Put your name in front of students preparing for this exam.Advertise →