CIMA BA2 · Chapter 7 · Question 14 of 14
Variable production overheads are absorbed at $4 per labour hour worked, and the standard time is 2 labour hours per unit. In a period, employees were paid for 19,800 hours, but 600 of these hours were idle time because of a machine breakdown. Variable overheads are incurred only when labour is working. Actual output was 9,800 units. What is the variable overhead EFFICIENCY variance?
Test yourself: pick an answer
Reveal answer & explanation
Correct answer: C) $1,600 favourable
Explanation
Hours actually worked = 19,800 - 600 = 19,200. Standard hours for actual output = 9,800 x 2 = 19,600. Variable overhead efficiency variance = (19,600 - 19,200) x $4 = $1,600 favourable, because the output took fewer hours than standard. Using hours paid (19,800) would wrongly give $800 adverse; idle hours carry no variable overhead, so they are excluded.
More Standard costing and variance analysis MCQs
- Q2A company purchased 8,400 kg of material for $39,480. The standard price is $4.80 per kg. What is the material price variance?
- Q3A company produced 2,000 units in a period. The standard usage is 4 kg of material per unit at a standard price of $4.80 per kg, and 8,300…
- Q4A team was paid $63,900 for 3,600 hours worked. The standard rate is $17.50 per hour and each unit should take 3 standard hours. Output…
- Q5Employees were paid for 5,000 hours, but because of a machine breakdown only 4,700 hours were worked. The standard rate is $15 per hour…
- Q6Variable production overheads are absorbed at $6 per labour hour worked. In a period, 4,700 labour hours were worked and actual variable…
